Money pit: $3B in cost overruns for Coast Guard's Deepwater procurement
The Coast Guard's Deepwater asset procurement program has seen its costs skyrocket while its performance capabilities degrade, according to a new report from the GAO.
The cost of the Coast Guard’s Deepwater asset acquisition program has risen to about $28 billion, and the agency still does not have a handle on determining its overall expenses and performance capabilities, according to a new report from the Government Accountability Office.
The complex procurement of cutters, patrol boats, helicopters, aircraft and other assets started in 2002 and originally was expected to cost $17 billion. In 2007, the Coast Guard rejected eight patrol boats as structurally defective and took over as lead systems integrator. The Coast Guard also recalculated the baseline cost of the program at $24 billion.
In today’s report, the GAO said baseline costs have increased to $28 billion—$3.8 billion over the $24.2 billion 2007 baseline. At the same time, performance capabilities have degraded.
“Currently, the Deepwater program exceeds the 2007 cost and schedule baselines and, given revisions to performance parameters for certain assets, it is unlikely to meet system-level performance baselines,” the report said.
The computation of baselines has been complicated by the reduction in projected service life of the new assets. With shorter service lives, life-cycle costs have dropped.
Related stories
Coast Guard hopes third time is the charm for troubled Deepwater procurement
False Claims Act lawsuit filed against Deepwater contractors
Even so, costs could expand further. “Costs could continue to grow as four assets currently lack revised cost baselines,” the GAO wrote. In addition, schedules for delivery of some of the assets are likely to be pushed back by several years.
“Overall, the 2007 baseline may not be achievable, as the Coast Guard has redefined or eliminated key performance indicators for many individual assets, while significant uncertainties surround other assets. Further[more], a planned analysis to reassess the overall fleet mix for Deepwater was not completed as planned,” the report said.
The GAO recommended that the Coast Guard complete an overall assessment “that clarifies the quantities, mix and cost of assets needed to meet requirements, given that the current Deepwater baseline is no longer feasible, and that the results be reported to Congress.” Department officials agreed with the recommendation.




