Nuclear Agency Faulted in Nonproliferation Cost Overruns

Congressional auditors on Thursday faulted the Energy Department agency for not having a good handle on why costs have risen so much for the South Carolina project.

Congressional auditors on Thursday faulted the Energy Department agency for not having a good handle on why costs have risen so much for the South Carolina project. // Flickr user Savannah River Site

A U.S. Congress watchdog is faulting the Energy Department for not having a clear idea why costs have risen so much on a key nonproliferation program.

The department's semiautonomous National Nuclear Security Administration forecasts a roughly $3 billion increase in the cost to its efforts to dispose of surplus weapons-grade plutonium by transforming it into atomic reactor fuel known as mixed oxide. Congress' Government Accountability Office in a new report released on Thursday said the agency had erred by not analyzing the "root causes" behind the cost increase.

The congressional auditors noted the nuclear weapons agency historically has "difficulty in completing projects within cost and schedule," which has contributed to a number of these initiatives facing "high risk of fraud, waste, abuse, and mismanagement."

The Mixed Oxide Fuel Fabrication Facility under construction at the Savannah River Site in South Carolina has seen its projected price tag rise from $4.9 billion to $7.7 billion. Several government officials and industry insiders recently told the Center for Public Integrity the final cost of building and operating the plant could reach as high as $30 billion. That projected expense reportedly has led the Obama administration to consider looking for another option for disposing of the 34 tons of plutonium that the MOX facility was intended to handle.

One major reason for the rising project costs is that the Energy Department in 2007 approved cost and schedule estimates when the overall designs were only 58 percent complete, according to the GAO report. Because of this early move, agency officials are now reporting that the expense of key components for the plant are on average 60 percent higher than was earlier estimated.

The report concluded there was not a clear understanding as to why the Energy Department approved the cost estimates when the design work was far from being complete. Having that knowledge could help NNSA officials in the future avoiding repeating the mistakes made with the mixed-oxide program, the auditors said.

Threatwatch Alert

Thousands of cyber attacks occur each day

See the latest threats

JOIN THE DISCUSSION

Close [ x ] More from Nextgov
 
 

Thank you for subscribing to newsletters from Nextgov.com.
We think these reports might interest you:

  • It’s Time for the Federal Government to Embrace Wireless and Mobility

    The United States has turned a corner on the adoption of mobile phones, tablets and other smart devices, outpacing traditional desktop and laptop sales by a wide margin. This issue brief discusses the state of wireless and mobility in federal government and outlines why now is the time to embrace these technologies in government.

    Download
  • Featured Content from RSA Conference: Dissed by NIST

    Learn more about the latest draft of the U.S. National Institute of Standards and Technology guidance document on authentication and lifecycle management.

    Download
  • A New Security Architecture for Federal Networks

    Federal government networks are under constant attack, and the number of those attacks is increasing. This issue brief discusses today's threats and a new model for the future.

    Download
  • Going Agile:Revolutionizing Federal Digital Services Delivery

    Here’s one indication that times have changed: Harriet Tubman is going to be the next face of the twenty dollar bill. Another sign of change? The way in which the federal government arrived at that decision.

    Download
  • Software-Defined Networking

    So many demands are being placed on federal information technology networks, which must handle vast amounts of data, accommodate voice and video, and cope with a multitude of highly connected devices while keeping government information secure from cyber threats. This issue brief discusses the state of SDN in the federal government and the path forward.

    Download
  • The New IP: Moving Government Agencies Toward the Network of The Future

    Federal IT managers are looking to modernize legacy network infrastructures that are taxed by growing demands from mobile devices, video, vast amounts of data, and more. This issue brief discusses the federal government network landscape, as well as market, financial force drivers for network modernization.

    Download

When you download a report, your information may be shared with the underwriters of that document.